Update for the works we are undertaking at Carrum Reserve:

1. Completed s base preparation and had signed off.

2. Surveyed surface for drainage system to commence next Wednesday.

3. Commenced preparing the foundations for the spoon drain on theoutside of the Oval.

4. Mapped Out conduit and located stomwater outlets.

 

The rain will be good to settle the sub base prior to us undertaking drainage and irrigation over the month of November.